Friday, April 11, 2014
Milton Madison Bridge
Last month I was down in Kentucky and was part of the team which inspected the bridge after the bearing dislodged. The bridge has now been repaired and slid into its final location.
Here are some videos of the bridges construction and moves:
Bridge phase animation
Ramp demo
Center span demo
Bridge lifted into place
Approach span slide
Bridge slide
Thursday, April 10, 2014
Bird Problems
I know most bridges I have worked on have problems with pigeons or even a falcon but this one is new to me. Caltrans is having trouble demolishing the old bay bridge since cormorants are nesting at the eastern end.
Full article here
Monday, April 7, 2014
Overhead Tunnel Inspection
A few weeks ago we started the inspection of Tip O'Neill Tunnel in Boston. All of the work is conducted at night when the state is able to close down portions or all of the lanes in the tunnel.
The work from the bucket truck is pretty easy and clean. Mainly we have just had to worry about dressing warm since a few nights have dropped to 10°F (-12°C).
The dirty work is having to inspect the exhaust plenums which are considered to be permit required confined space. Much like their name suggests they are full of exhaust and caked with soot.